Bocce courts need a consistent, slightly crowned surface so water sheds to the sides rather than pooling in the playing lane. A local court builder checks your site’s natural slope and soil type during the base-condition assessment. That reading determines excavation depth and the compaction spec for the crushed-aggregate sub-base.
Surface material choices include oyster shell flour, decomposed granite, or crushed limestone, each with different compaction rates and drainage characteristics. The written estimate names the material, layer thickness, and compaction method. Redwood or composite sideboards are anchored into the sub-base to hold the surface material in place.
Once the surface is compacted and levelled, the builder checks the crown profile and drainage slope before signing off. Regulation dimensions run 13 ft wide by 91 ft long, but the estimate can spec a shorter court if your space requires it. A final walkthrough confirms level, drainage, and sideboard anchor placement.